salam~
hehe..its not about the song by miley cyrus..but it's me doing the climb..hehe~
en din invited me to join the meeting with Siemens discussing bout the transformer again..it's actually to negotiate the price again..i think they have made up their mind about the type and made..so i think its the Siemens after all..so..need to wait for another 10 weeks i guess~
then en sahar asked me to follow him with hj radzi to Cargo Agent A..they are planning on changing all the lightning arresters that was stolen..it's kinda weird when looking at the security and all..so assumption made..it's done by the people working inside the complex itself..weird when people now don't mind taking others belongings just for money~
the process for a tender to be opened will involve:
1. visiting the site
2. estimation on the things to be done
3. calling min 3 contractors
4. 3 quotations
5. selection
6. request work order
7. request work approval from subang; with the budget approval
8. work done
9. report
that's what i understood..i will try to ask some example to put in the report later~